Current Events Bell Ringer for Grades 6–8: NASA’s 200-second test of an RS-25 Moon rocket engine
A free current events bell ringer for grades 6–8. Put the prompt on the board as students walk in, give them three to five minutes, then go over it together. The answer and teacher notes are in the box below the prompt.
The prompt
On November 18, NASA fired an RS-25 rocket engine at the Fred Haise Test Stand at Stennis Space Center near Bay St. Louis, Mississippi. The engine, a developmental model called No. 10001 that will not fly in space, ran for its full scheduled time of three minutes and 20 seconds. RS-25 engines power NASA's SLS (Space Launch System) Moon rocket. Each SLS uses four of these engines, which together produce up to 2 million pounds of thrust. Testing like this supports NASA's Artemis IV mission, scheduled for 2028 from Kennedy Space Center in Florida. (a) Show that three minutes and 20 seconds equals 200 seconds. (b) If the thrust is shared equally, about how much thrust does each engine produce? (c) How many years from now is Artemis IV scheduled? (d) Why would engineers fire an engine on the ground, strapped to a test stand, before using that design on a real rocket? (e) Why might NASA build and test an engine that will never go to space?
Answer and teacher notes
(a) 3 × 60 = 180 seconds; 180 + 20 = 200 seconds ✓. (b) 2,000,000 ÷ 4 = about 500,000 pounds of thrust each. (c) 2028 − 2026 = 2 years. (d) Answers will vary: it is safer and cheaper to find problems on the ground, where sensors can measure everything and no crew is at risk. (e) Answers will vary: a test engine lets engineers try new parts, push limits, and learn how the design behaves without risking an engine meant for flight.
Thrust is the push a rocket engine makes by blasting hot gas out the back; by Newton's third law, the gas pushes the rocket the other way. The article lists L3Harris Technologies as the engine contractor. Common mistake on (a): treating 3 minutes 20 seconds as 3.20 minutes or 320 seconds. Common mistake on (b): forgetting the article says "up to," so 500,000 pounds is an average of the maximum, not an exact figure for each engine. Extension: why does a rocket need so much thrust just to lift off? (It has to push harder than its own enormous weight, which gravity pulls down.)
Source: ScienceDaily (from NASA): NASA's Powerful Moon Rocket Engine Roars Through a Dramatic 200-Second Test (November 18, 2026, test, RS-25 No. 10001 developmental engine, Fred Haise Test Stand at Stennis Space Center near Bay St. Louis, Mississippi, three minutes and 20 seconds (200 seconds), four engines per SLS producing up to 2 million pounds of thrust, Artemis IV scheduled for 2028 from Kennedy Space Center, L3Harris Technologies)
Free to use. Copy, print, project or adapt any of these for your students. If you share them online, please credit Daily Bell Ringers with a link. Not for resale. License: CC BY-NC 4.0.